The below-grade takeoff checklist: 12 items estimators miss

By the Division 7 Estimating team · · 7 min read

The field area is the easy part of a below-grade takeoff. Walls are walls; slabs are slabs. The jobs that go sideways are the ones where the edges of the scope — the terminations, transitions, and accessories — never made it into the quantity column. Here's the checklist we run on every below-grade takeoff.

The checklist

  1. Terminations at grade. Termination bar, counterflashing, or sealant reglet — measured in LF, priced with fasteners and sealant. If the detail shows it, the takeoff carries it.
  2. Inside and outside corners. Most sheet systems want reinforcement or pre-formed pieces at every corner. Count them; don't average them.
  3. Penetrations. Every pipe, conduit bank, tieback, and form tie treatment. On a congested foundation, penetration details can be a bigger labor number than the field membrane.
  4. Waterstop. Construction joints, cold joints, pour breaks — walk the pour sequence, not just the plan. PVC, hydrophilic, or injectable hose all price differently.
  5. Protection board. It's rarely drawn but always required before backfill. Field area + laps, and note who backfills — your schedule depends on it.
  6. Drainage composite. Sheet drain SF, plus the fittings nobody draws: end caps, outlets, and connections to the footing drain.
  7. Detail strips and cants. Fluid-applied systems typically want detail coats at transitions — LF that consumes real material and real labor.
  8. Elevator pits and sumps. Small SF, brutal access, different system than the walls half the time. Price them as their own scope with their own production rate.
  9. Mockups and testing. Spec sections love flood tests, adhesion tests, and mockup panels. They're in Division 07 requirements even when they're not on the drawings.
  10. Substrate condition allowances. Honeycomb repair, form tie patching, laitance removal — decide what's included, and say so in the exclusions if it's not.
  11. Sequencing and remobilizations. Below-grade work follows the concrete. If the pour schedule means four wall pours, that's four mobilizations of detail work — not one.
  12. Blindside conditions. Shotcrete or soldier-pile walls flip the system and the labor model entirely. Confirm which walls are blindside before you price a single SF.

Make the checklist automatic

A checklist only works if it runs every time. That's the argument for estimating worksheets that carry the accessories with the system: when the deck coating worksheet knows every field SF drags primer, base, texture, and top coats with their own coverage and packaging — and the below-grade worksheet won't let field area exist without terminations — the "we missed the waterstop" conversation stops happening.

That's how Division 7 Estimating's worksheets are built. And if you'd rather have someone else run the checklist this week, our takeoff team starts at $150.